How Are Construction Estimates Typically Organized?

How Are Construction Estimates Typically Organized?

Construction estimation calculates a project’s expected costs, including materials, labor, equipment, and other expenses. Estimates help construction stakeholders, contractors, and owners make more informed decisions and manage finances effectively. Construction estimates are typically organized by breaking the project into work packages or sections. Then, they include the costs of each work, such as materials, labor, equipment, and overhead, with contingencies added for unexpected expenses. 

This comprehensive blog post will discuss the organization of typical construction estimates. We will also help you locate the best construction estimating services in NYC. Let’s begin this fascinating discussion by breaking down the construction estimates: 

Breakdown of Construction Estimates:

Construction estimates typically organize costs into direct and indirect categories. Direct costs encompass materials, labor, and subcontractors, while indirect costs include overhead, insurance, and profit. Let’s explore the complete breakdown of a construction estimate.

  1. Project Breakdown:

The first step in organizing a construction estimate is to divide it into more manageable sections or work packages. For example, suppose you are estimating a home. In that case, you would split the estimate into different sections regarding work packages such as foundation, framing, roofing, electrical, and plumbing. 

  1. Material Costs:

Once you have a project breakdown, the next step in the construction estimates organization is to allocate the material cost for each section. List the material required for each section, including quantities, unit prices, and potential discounts. 

For instance, if you are estimating the material costs for the foundation of a home construction project, you would detail it as follows:  

Materials Required for Foundation Work:  

  • Concrete (ReadyMix, 4000 PSI)—50 cubic yards @ $150 per cubic yard = $7,500  
  • Rebar (Steel Reinforcement Bars, 4, 20ft each) – 100 pieces @ $12 each = $1,200  
  • Gravel (for base layer and drainage)—20 tons @ $30 per ton = $600  
  • Formwork Plywood (for concrete molds)—50 sheets @ $25 each = $1,250  
  • Anchor Bolts (for securing the structure)—50 pieces @ $5 each = $250  
  • Waterproofing Membrane (for foundation walls)–10 rolls @ $100 each = $1,000  

Total Estimated Material Cost: $11,800  

If the contractor negotiates a 5% bulk discount on materials over $10,000, the final cost might drop to $11,210. Considering such discounts provides a more accurate and cost-effective estimate. 

Note: The prices listed here are for informational purposes only! 

  1. Labor Costs:

Construction estimates are typically organized by estimating the labor hours needed for each section. Make sure you add the appropriate labor hours required, labor rates, and potential subcontractors. NYC is one of the most expensive cities when it comes to skilled labor, so make sure you add realistic and updated labor rates. For more accurate rates, check the market, add transportation, and consider other factors that might increase labor costs. 

For example, if you are estimating the labor costs for the framing of a home construction project, you would break it down as follows:

Labor Costs for Framing Work:

  • Carpenter (Lead Framer, Skilled Worker) – 120 hours @ $65 per hour = $7,800
  • Carpenter’s Helper (Assistant, SemiSkilled Worker) – 100 hours @ $40 per hour = $4,000
  • Subcontractor (Specialized Framing Contractor for Complex Structures) – Fixed contract price = $5,500
  • Additional Costs (Transportation & Site Setup for Crew) – $800

Total Estimated Labor Cost for Framing Work: $18,100

Since NYC has high labor costs, it’s crucial to consider factors like potential overtime, union wage requirements, and additional expenses such as transportation. Checking the latest market rates ensures that the estimate remains accurate and realistic.

Note: The prices listed here are for informational purposes only! 

  1. Equipment Costs:

Identify the equipment needed for each section and estimate its rental and ownership costs. This will help construction estimators and managers make more precise and accurate estimations. 

For instance, if you are estimating the equipment costs for the excavation and site preparation of a home construction project, you would detail it as follows:  

Equipment Needed for Excavation and Site Preparation:  

  • Excavator (for digging foundation trenches and leveling the site) —Rental: $1,500 per week (Estimated 2 weeks) = $3,000  
  • Bulldozer (for grading and clearing the land) — Rental: $1,800 per week (Estimated 2 weeks) = $3,600  
  • Dump Truck (for removing excess soil and debris)—Rental: $900 per week (Estimated 2 weeks) = $1,800  
  • Plate Compactor (for soil compaction before foundation work)—Rental: $100 per day (Estimated 7 days) = $700  
  • Generator (for power supply at the site)—Ownership Cost: $5,000 (or Rental: $250 per week)  

Total Estimated Equipment Cost (Rental Basis): $9,100  

If the project is long-term, purchasing specific equipment (such as a generator) may be more cost-effective than renting. Comparing rental vs. ownership costs ensures a well-optimized budget for construction projects.

Note: The prices listed here are for informational purposes only! 

  1. Subcontractor and Overhead Costs:

A typical construction estimation organization’s fifth step is calculating the subcontractor and overhead costs. Therefore, obtain quotes from subcontractors for specialized work such as concrete, steel, electrical, or plumbing. For overhead costs, add indirect costs like administrative expenses, insurance, and utilities. 

  1. Contingency Plan:

Incorporate a buffer for unexpected expenses, generally 5–15% of the total cost. Review and finalize the estimate, making sure that all costs are included and that it remains realistic and competitive.

Bottom Line:

Construction estimation calculates the total cost required to complete any project. It includes all expenses, such as materials, labor, and equipment costs. The typical construction estimates organization starts by breaking the projects into work packages, including materials, labor, equipment, and other aspects of the construction estimates.

My Virtual Estimator is the leading construction estimation service provider in NYC. They excel in the industry, boasting years of experience and expert estimation services. Whether you’re a construction estimator, manager, or owner, they can assist you. Their team of experts provides precise construction estimates for various types of projects. Contact them for your construction estimation needs in New York City. Their experts consistently go above and beyond to provide exceptional construction services.